Services
We pay attention to every detail to build not just a house, but a "home you love" — for you and the people you cherish. From design to the selection of premium, eco-conscious materials, we build homes that are strong, durable, and built to last.
Home Construction Service Areas
Bangkok and vicinity
Bangkok, Samut Prakan, Pathum Thani, Nontaburi, Nakorn Pathom, Samut Sakhon
Northern
Nakhon Sawan, Phichit, Phitsanulok, Kamphaeng Phet, Sukhothai, Lamphun, Lampang, Chiangmai
Central
Ayudhaya, Angthong, Saraburi, Lopburi, Singhburi, Suphanburi, Uthaithani
Eastern
Nakon Nayok, Chachoengsao, Prachin Buri, Chon Buri, Rayong
Northeastern
Nakhon Ratchasima, Khon Kaen, Udonthani, Maha Sarakham, Kalasin Buri Ram, Surin, Si sa Ket, Ubonratchathani
Southern
Prachuap Khiri Khan, Chumphon, Surat Thani, Nakonsrithammarat
Service Conditions
Description
We will facilitate and provide services to clients who wish to construct the house as follows:
No.
Government liaison and utility connection services
Fee
(baht)
Security
(baht)
1
Apply for construction permit
(Company bear the expense)
-
-
2
Apply for house registration number
(Company bear the expense)
-
-
3
Apply for temporary water meter (Metropolitan)
Apply for temporary water meter (Provincial)
(Company bear the expense exclude service area extension fee)
5,350
3,600
-
-
5,350
-
4
Apply for temporary electricity meter (Metropolitan)
Apply for temporary electricity meter (Provincial)
(Company bear the expense exclude service area extension fee)
400
-
-
10,000
10,000
-
5
Apply for permanent water meter dia.1/2” (Metropolitan)
Apply for permanent water meter dia.1/2” (Provincial)
Customers bear the service area extension fee (if any) and
Customer shall be responsible for the service area extension and expenses (as per water authority’s official receipts)
107
535
.
-
6
Apply for permanent electricity meter (Metropolitan and Provincial)
15 Amps 1 Phase
Customer shall be responsible for the service area extension and expenses (as per water authority’s official receipts)
749
749
-
We will handle all the six items of expenses and services mentioned above on your behalf until completion. In the event that you wish to increase the electricity meter capacity beyond our standard specification, please inform us on the contract singing date or prior to the commencement of
Description
Description
Description
In case you are interested to apply for housing loan service, we are pleased to facilitate the Bank on your behalf. The major banks that provide special conditions for our customers are
Housing Loan Service
The basic conditions for housing loan are
1
The land must be free from any mortgage. In case there are co-owners, the co-owners must sign the letter of consent.
2
Land and building must be mortgaged to the bank. The owner must buy fire insurance policy with the insurer recommended by the bank
3
Your monthly income (include your spouse) should be 2.5 times of the amount t.o be paid to the bank. For example, if the amount to be paid monthly is 10,000 baht, your monthly income should be 25,000 baht (approximately).
Warranty
1
10 Years warranty for the main structure of the house. Exclude road works and area where loads are directly transferred to the ground which do not affect the structure integrity or pose any danger to occupants.
2
1 year warranty for general work, exclude natural depreciation of materials due to long used and misused.
3
5 years warranty for roof tiles (by the manufacturer and installer).
4
10 years warranty for rustproof roof structure (by the manufacturer and installer).
5
10 years warranty for Aluminum doors and windows’ color (by manufacturer).
If you decide to have the company build your house, the Application form for house building service should be filled and submitted. Detail as follow:
No
House Price
Advance payment
(Baht)
1
House price does not exceed 2 million baht
30,000
2
House price more than 2 million baht
50,000
Documents
1
4 copies of Title Deed with verified signature (the same size of original copy)
2
4 copies of ID card and house registration with verified signature
3
A copy of tax payment receipt with verified signature
Our survey officer will survey the land for construction and the access road in order to determine the building layout on the site in coordination with you. If the construction site cannot be accessed due to too narrow road, the advanced payment will be refunded.
When the land survey result, the list of standard materials and the house plan are agreed, the contract must be signed so we can proceed for the construction permit.
The advance payment will be refunded on the day the contract is signed. If there is any additional construction made after the contract is signed, the company will propose the quotation, and the payment must be made before the additional construction starts.
The construction period under the contract shall commence 45 days after the contract signing date and full payment of the contract installment. (During this 45-day period, we will prepare architectural drawing, submit application for construction permits with the relevant authorities.)
Duration of construction for precast load-bearing wall structure.
Column 2
Column 3
No
House Price
Duration of construction
1
House price not exceed 2 million baht
120 – 150 days
2
House price from 2 million baht but not exceed 3 million baht
150 - 180 days
Duration of construction for cast in place structure.
House Price
Duration of construction
No
House Price
Duration of construction
1
House price not exceed 2 million baht
210 – 240 days
2
House price from 2 million baht but not exceed 3 million baht
240 - 270 days
Remark:
For your confidence and to confirm that the company will complete the construction within the duration stated in the contract, the company agrees to pay the fine 0.01% of the house price if the company cannot hand over the house to the customers on time.
Installment
Payment
Description
1
15%
On the contract signing date
2
20%
Completiong of setting out, piling work and foundation work
3
20%
Completion of Load- Bearing Wall concrete structure installation and galvanized roof truss installation.
4
20%
Completion of eaves installation (if any), roofing materials installation, skim coat plastering, interior plumbing (with pressure tested) and treatment tank and drainage pipe installation.
5
20%
Completion of bathroom wall and floor tiles installation, doors and windows installation, interior wiring installation, plumbing and sanitaryware installation, interior and exteior ceiling installation.
6
5%
Completion and handover of the house.
Installament
Payment
Description
Sign the contract
10
On the contract signing date
1
20
Completion of setting out, piling work, foundation work and ground beams.
2
20
Completion of reinforced concrete structure work – column, floor, roof beam, concrete roof slab (if any) and galvanized roof truss installation.
3
20
Completion of eaves installation (if any), roofing material installation, brick laying, interior plumbing (with pressure test), PVC conduit installation (for wiring) and 50% interior wall plastering
4
15
Completion of wall plastering, primer painting, exterior doors and windows installation, interior wiring, bathroom wall tiling, interior and exterior ceiling and soffit installation.
5
10
Completion of bathroom floor tiling, interior doors installation, sanitary wears installation, treatment tank and drainage pipe installation, 1 final paint and exterior wall decorative material installation (if any)
6
5
Completion and handover of the house.